THE OIL AND GAS ACT
(C.C.S.M. c. 034
)

Regulation 111/94
Registered
June 6, 1994

The Drilling and Production
Regulations 111/94 as
amended by
 M.R. 51/95
 M.R. 145/98
 M.R. 116/2001

Regulations
gold dotCrown Disposition Regulation
gold dotCrown Royalty & Incentives Regulation
gold dotDrilling & Production Regulation
gold dotGeophysical Regulation
gold dotLandspraying While Drilling (LWD) Guidelines
gold dotPetroleum Fiscal Regime - Incentive Program
gold dotOil & Gas Production Tax Act Regulation
Acts
gold dot
Bill 21 - The Oil and Gas Amendment and
Oil and Gas Production Tax Amendment Act

gold dotOrders under The Oil and Gas Act
gold dotThe Oil and Gas Act
gold dotOil and Gas Production Tax Act

SCHEDULE C
(Subsections 9(1), 75(4), and 85(1)
Drilling and Production Regulation Table of Contents

Table of Minimum Distance Requirements
Note: The distances in the table are expressed in metres

To: Well Flame Type Equipment Internal Compustion Engine Flare Pit
and Flare Stack
Oil Storage Tank Surface
Improvement
Except Well,
Flow Line or Road Allowance
Water
Covered
Area
Road
Allowance - Provincial or Municipal
Air Shut Off No Air Shut off
From:                  
Well 5 25 5 10 25 25 75 100 45
BOP Manifold 3 -- -- -- 15 -- -- -- 45
BOP Remote Control 15 -- -- -- 15 -- -- -- 45
Flame-
Type Equipment
25 -- -- -- 25 25 -- -- 45
Drilling Fluid Pit
or Tank
5 25 -- -- 10 -- 75 100 45
Flare Pit and Flare Stack 25 25 5 10 -- -- 100 100 45
Emergency Storage Pit 25 25 -- -- 25 -- 75 100 45
Service or Test Tank 25 25 5 10 25 -- 75 100 45
Oil
Storage Tank
25 25 5 10 25 -- 75 100 45
Vented
Salt Water tank
10 5 5 5 25 -- 75 100 45
Process Vessell 25 -- -- -- 25 25 75 100 45


SCHEDULE D
Schdule D is repealed

 

SCHEDULE E
(Subsections 21(2) and 22(1), and clauses 24(1)(b) and 25(1)(a))
Requirements for a Drilling Blow-out Prevention System
Drilling and Production Regulation Table of Contents

Note:

1. In the diagrams,

"A" means an annular type blow-out preventer;

"R" means a single ram type blow-out preventer with one set of rams, either blank or for pipe;

"S" means a drilling spool with flanged side outlet connections for bleed-off and kill lines.

2. The line sizes indicated in the diagrams are the minimum nominal diameter required.

3. The portion of the bleed-off system from the drilling spool to the choke manifold must be constructed with flanged pipe connections. Threaded fittings may be used for the remainder of the bleed-off system.

4. The manifold system must be constructed to provide flow paths equivalent to those indicated in the diagram.

5. The bleed-off system must contain only the straight pipe, or 90° bends constructed of tees and crosses that are blocked on fluid turns.

back to top